1500HP SCR Control System Project
The 1500HP SCR Control System Project was executed for PT Bina Mitra Artha (BMA) to support the operation of its drilling rig. The Purchase Order was issued by PT Bina Mitra Artha in early February 2025.
The SCR Control System unit was delivered and arrived in Indonesia in August 2025. Following delivery, installation, testing, and commissioning activities were carried out to ensure compliance with operational requirements and system performance standards.
The project was successfully completed with final commissioning and handover conducted in September 2025, enabling the drilling rig to operate with a reliable and efficient power control system.
Scope of work
Oil & Gas
Project Years
2025
Project Delivered
- 1500HP SCR Control System